Direct Answer

How should Level-1/2/3 metering be built? A three-tier metering system — Level 1 is installed at the incoming line/transformer (enterprise total consumption and settlement), Level 2 at workshops/buildings/main branch circuits (regional accounting), and Level 3 at major production lines/key equipment (assessment and diagnosis); the higher the tier, the coarser it is, and the investment is concentrated at Level 2.

A scenario: A factory wants to build a metering system — installing only the total meter is too coarse and installing down to every socket costs too much — nobody knows which tier the meters should go on. The design logic is that Level 1 manages the total, Level 2 manages regions and Level 3 manages equipment — three tiers with their own purposes — the investment is concentrated at Level 2 and each tier can be verified against the others.

1. The Definition and Installation Points of Three-Tier Metering

Level 1 metering — incoming/transformer: installed at the total incoming line and both sides of the transformer; The purpose of Level 1 — enterprise total: the basis of plant-wide total consumption and settlement; Level 2 metering — workshops/buildings: installed at workshops, buildings and main branch circuits; The purpose of Level 2 — regional accounting: workshop/building-level consumption accounting and comparison; Level 3 metering — production lines/equipment: installed at major production lines and key equipment; The purpose of Level 3 — assessment and diagnosis: equipment-level assessment, unit-consumption diagnosis and detailed analysis.

In one sentence: three-tier metering is Level 1 for the total (incoming/transformer), Level 2 for regions (workshops/buildings) and Level 3 for equipment (production lines/key equipment).

Versus single-tier metering — three tiers add regional accounting, equipment diagnosis and tier-by-tier anomaly location, and the investment is phased and growable. An example: A factory builds Level 1 at the incoming line and 2 transformers, Level 2 at 6 workshops and Level 3 at 12 production lines. The logic is that tiers are installed by purpose — which tier you install depends on which question you need to answer.

2. The Purpose and Accuracy Requirement of Each Tier

Level 1 accuracy — settlement level: the highest accuracy requirement (Class 0.5/0.2S); The purpose of Level 1 — external settlement: the basis of settlement with the grid and the superior unit; Level 2 accuracy — assessment level: medium accuracy (Class 1.0 is enough); The purpose of Level 2 — internal accounting: workshop assessment, regional comparison and cost allocation; Level 3 accuracy — diagnosis level: enough for diagnosis (Class 1.0); The purpose of Level 3 — detailed analysis: equipment unit consumption, production-line efficiency and anomaly location.

In one sentence: the accuracy is settlement level at Tier 1 (0.5/0.2S), assessment level at Tier 2 (1.0) and diagnosis level at Tier 3 (1.0).

The cost of accuracy — a Class 0.5 meter at Level 1 costs noticeably more than a Class 1.0 — use high accuracy only on settlement circuits.

An example: A factory configures Class 0.5 at Level 1 and Class 1.0 at Levels 2/3 — cost is reasonable. The logic is that accuracy follows the purpose — no wasted accuracy, controlled cost.

3. How the Three Tiers Are Rolled Up and Verified

Roll-up one, Level 3 to Level 2 — equipment roll-up: the Level-3 total should be roughly equal to Level 2; Roll-up two, Level 2 to Level 1 — regional roll-up: the Level-2 total should be roughly equal to Level 1; Roll-up three, the loss item — difference attribution: the inter-tier difference is attributed to losses and unmetered items; Verification one, the balance rate — computed tier by tier: each tier's balance rate is computed independently and tracked continuously; Verification two, anomaly location — narrowed tier by tier: whichever tier is out of balance, the problem is below that tier.

In one sentence: the roll-up is Level 3 to Level 2 to Level 1, tier by tier — the inter-tier difference is attributed to losses and verified with the balance rate.

The verification actions — Level 3 vs Level 2 and Level 2 vs Level 1 by rolled-up comparison, plus the balance rate (95%-99% healthy). The verification period — monthly must-check: verify tier by tier at month-start and archive the difference records.

The accuracy note — tier-by-tier verification does not require 100% equality: a 2%-5% inter-tier difference is acceptable losses and unmetered items.

An example: A factory verifies tier by tier: Level 3 vs Level 2 differs by 3% and Level 2 vs Level 1 by 2% — both within reasonable losses. The logic is that tiers can be verified one by one — whichever is out of balance, check below it — far clearer than a one-pot comparison.

4. Investment Allocation and Phased Construction Suggestions

Investment one, the Level-1 share — the small share: few Level-1 points, small investment share; Investment two, the Level-2 share — the large share: Level 2 covers many regions and holds the most investment; Investment three, the Level-3 share — flexible: many Level-3 points, expanded by need in phases; Phase one — Level 1 plus Level 2: build the total consumption and regional accounting first; Phase two — Level 3 priorities: major production lines and key equipment are added gradually; The meaning of phasing — trunk before branches: investment concentrated at Level 2, Level 3 expanded by need.

In one sentence: the investment is a small share for Level 1, a large share for Level 2 and flexible for Level 3 — build Level 1 and Level 2 in phase one and expand Level 3 in phase two.

An example: A factory phases it: phase one installs Level 1 plus Level 2 (about 70% of the investment) and phase two adds Level 3 on priority lines (30%). The logic is that Level 2 is the main battlefield and the most worthwhile investment — build the trunk first, expand Level 3 by need.

5. The Interface between the Three-Tier System and the Supervision Center Platform

Interface one, data access — unified access: meter data of all tiers is uniformly accessed into the supervision center; Interface two, tier modeling — tree modeling: the platform builds a "Level 1 to Level 2 to Level 3" tree; Interface three, automatic roll-up — tier-by-tier roll-up: the platform automatically rolls up tier by tier and computes the balance rate; Interface four, tiered reports — by-tier reports: total, regional and equipment reports with separate permissions; Interface five, anomaly push — tier location: anomalies are automatically located to the specific tier and equipment.

In one sentence: the platform interface is unified access, tier modeling, automatic roll-up, tiered reports and tier location.

An example: A factory platform builds a Level-1-to-3 tree, rolls up automatically and locates anomalies to a workshop and equipment. The logic is that tree modeling layers the data and automation saves verification labor — the platform is the nervous system of the system.

6. A Solution Example: How a Park Builds It

The current state — a park: 1 total incoming line, 3 buildings and 6 production lines; Level 1 — the total incoming line plus transformers: Class 0.5 meters for settlement; Level 2 — 1 meter per building: Class 1.0 meters for building accounting; Level 3 — 1 meter per production line: Class 1.0 meters for production-line diagnosis; Roll-up — automatic platform verification: building totals vs the total meter, production-line totals vs the building meters; The effect — three layers of data: totals, regions and equipment all have numbers.

In one sentence: this park has 1 Level-1 point, 3 Level-2 points and 6 Level-3 points — the platform verifies tier by tier and the data is viewable on three layers.

The growth path of the park — later new production lines directly add meters at Level 3 and the platform automatically includes them in the roll-up.

An example: After the park goes live, building accounting is clear and anomalies are located the same day. The logic is that the structure gives three viewable layers — later expansion only adds meters at the corresponding tier — the system is growable.

7. Back to YESLON: How to Configure ESA, ZSA and ESX

The ESA role — the Level-1 mainstay: settlement-level high-accuracy metering; The ZSA role — the Level-2/3 mainstay: embedded meters for in-cabinet itemization; The ESX role — edge aggregation: nearby acquisition, edge computing and store-and-forward; The configuration logic — by tier: ESA at Level 1, ZSA at Level 2/3 and ESX for aggregation; The solution support — the supervision center: tier modeling, automatic roll-up and balance-rate verification.

In one sentence: the YESLON configuration is ESA at Level 1, ZSA at Level 2/3, ESX for edge aggregation and tier modeling on the supervision center.

The implementation order of the configuration — step one, select the products by tier; step two, deploy the ESX edge gateway on site; step three, build the tier model and configure the roll-up rules on the supervision center; step four, set the balance-rate threshold and accept.

An example: A factory configures ESA Class 0.5 at Level 1, ZSA at Level 2/3 and ESX for aggregation. The logic is that products plus the platform form a complete three-tier system.

8. Self-Check: Four Questions to See Whether the Three-Tier System Is Right

Question one, are the tiers clear — tiers: are the Level-1/2/3 positions explicit; Question two, is the accuracy correct — accuracy: is each tier's accuracy matched to its purpose; Question three, is it verifiable — roll-up: is the tier-by-tier roll-up and verification connected; Question four, is it growable — expansion: is later point expansion convenient.

In one sentence: the four questions are tiers, accuracy, verification and expansion — all answered, the three-tier system stands.

The supporting action of the self-check — pre-commission review: go through the four-question list item by item and fill what is missing.

A self-check example: A factory answers the four questions — the tiers are clear, the accuracy is correct, the verification is connected and the expansion is convenient — the three-tier system is built at once — the pre-commission review passes. A three-tier metering system — Level 1 installed at the incoming line/transformer (enterprise total and settlement, Class 0.5/0.2S), Level 2 at workshops/buildings/main branch circuits (regional accounting, Class 1.0), and Level 3 at major production lines/key equipment (assessment and diagnosis, Class 1.0); the higher the tier, the coarser it is, and the investment is concentrated at Level 2 (build Level 1 and Level 2 in phase one and expand Level 3 in phase two); roll up and verify from Level 3 to Level 2 to Level 1, attribute the inter-tier difference to losses and compute the balance rate tier by tier — Level 1 manages the total, Level 2 manages regions and Level 3 manages equipment — every layer has numbers and every kilowatt-hour has a destination.

Scope and Limitations

  • The conclusions in this article are intended for LV distribution and electrical-safety sites. Standard numbers (GB/T 23331, DL/T 448) refer to their currently effective editions, and product parameters follow the latest FEXLINK selection handbook and product knowledge base.
  • Quantitative criteria (protection zone, discharge and residual voltage, earth resistance, thresholds and grading) hold under the preconditions stated in this article. Where the site voltage level, earthing arrangement, environmental category or load profile differs, the figures must be recalculated. Specific configurations involving ESA all-element smart meter, ZSA embedded smart meter, ESX edge gateway should be verified against actual circuit parameters.
  • Specific product models and parameters are subject to the latest selection handbook and product knowledge base; this article does not constitute selection or procurement advice.
  • Standard numbers cited here refer to the currently effective editions; when a standard is revised, the related quantitative conclusions must be re-checked.
  • Deployment and implementation for specific projects must be carried out by qualified engineers based on site survey and design drawings.

Frequently Asked Questions

How to Build Level-1/2/3 Metering

A three-tier metering system — Level 1 is installed at the incoming line/transformer (enterprise total consumption and settlement)