Direct Answer
A 63-point alarm pops up on the big screen — does the operator act now or just log it? Match it against the Qianzhi bands: 85-100 Normal (no action), 70-84 Watch (log and observe), 55-69 YJ1 (schedule an inspection within 24 hours), 40-54 YJ2 (handle in the current shift), 20-39 BJ1 (plan a shutdown repair within 48 hours), 0-19 BJ2 (shut down immediately). Lower scores mean faster action; a score crossing a band boundary triggers escalation. Every alarm also carries a standard-code reference and a four-dimension impact label telling the operator what the basis is, what is affected, and how urgent it is.
A scenario: A switch-room operator sees two alarms — one at 62 and one at 35. By the bands: 62 is YJ1 — schedule an inspection within 24 hours, no middle-of-the-night trip; 35 is BJ1 — plan a shutdown repair within 48 hours and slot it in now. The two alarms demand different actions; the operator stops debating "should I go" and executes the SLA.
1. What the Bands Are For: Why Continuous Scores
The point of continuous scores — not a good/bad binary: a 0-100 risk score showing how the hazard severity changes continuously; Versus threshold alarms — thresholds only say "over limit / normal": a continuous score shows "approaching the limit"; The role of bands — map continuous scores to discrete actions: every band has a clear SLA, so operators do not guess; How scores are built — model-based scoring: data features, equipment condition and historical patterns weighted together; The boundary of scores — not absolute truth: bands are action suggestions; the field situation always outranks them.
In one sentence: continuous scores answer "how severe", bands answer "what to do" — together they turn alarms from "whether it rings" into "how urgent, what action".
A comparison example: A traditional threshold alarm rings only when current crosses the limit; before that, silence. A Qianzhi continuous score slides from 88 to 76 to 64 while the current is still rising — the trend is visible and the action comes earlier. Continuous scores do not make alarms complex; they turn "silence before the critical point" into "actionable lead time".
2. The Six Bands and Action SLA Table
85-100 Normal — no action: log and keep the record, routine observation; 70-84 Watch — log and observe: track the trend, no action scheduled; 55-69 YJ1 — alarm level one: schedule an inspection within 24 hours; 40-54 YJ2 — alarm level two: handle in the current shift; 20-39 BJ1 — alarm level one: plan a shutdown repair within 48 hours; 0-19 BJ2 — alarm level two: shut down immediately.
| Band | Level | Action SLA | Typical scenario |
|---|---|---|---|
| 85-100 | Normal | no action, keep record | equipment running healthy |
| 70-84 | Watch | log and observe | slight indicator drift |
| 55-69 | YJ1 | inspect within 24 hours | abnormal trend confirmed |
| 40-54 | YJ2 | handle in current shift | hazard clear, intervention needed |
| 20-39 | BJ1 | shutdown repair within 48 hours | high risk persists |
| 0-19 | BJ2 | shut down immediately | near-accident state |
In one sentence: six bands are Normal / Watch / YJ1 / YJ2 / BJ1 / BJ2 — lower scores mean faster action — read the band first, then the score, then the labels, and the response will not go wrong.
A comparison example: One transformer oil temperature — 88 (Normal, observe); three days later 72 (Watch, log); a week later 61 (YJ1, schedule inspection); two weeks later 45 (YJ2, handle in shift — inspection finds the cooling fan failed). Every band has an explicit SLA — not a vague "should deal with it".
3. The 85-100 Normal Band: No Action, But Keep Records
What Normal means — equipment running healthy: indicators in the reasonable range, the model sees no anomaly; What no action means — no staff dispatch: follow the routine inspection cycle; Why records matter — baseline accumulation: healthy running data is the reference frame for judging anomalies; How records are kept — alarm archive: score, indicators and time all retained; The boundary of Normal — sliding to 84 and below: the Watch band starts and the action changes.
In one sentence: Normal is healthy running, no action and record retention — the more healthy baseline data, the more accurate anomaly judgment.
A record example: One switchboard ran at 88-95 for three months; that baseline told the model what this cabinet normally looks like; the day the score dropped to 79, the model recognized it at once. No healthy-baseline accumulation, no anomaly judgment — keeping records is not formality; it is model training data.
4. The 70-84 Watch Band: Log and Observe
What Watch means — slight indicator drift: not yet an alarm, but the trend deserves attention; What Watch does — log and observe: the operator registers it in the log and adds it to daily attention; Why no immediate action — the score has not reached the alarm line: most drift recovers by itself, and overreacting costs more; The boundary of Watch — sliding to 69: upgrade to YJ1, action changes from observe to inspect; The trap of Watch — logging forever without review: observation logs no one reads are as good as none.
In one sentence: Watch is log and observe — no action does not mean no management — continuous decline escalates, and observation logs must be reviewed.
A Watch example: One motor's vibration slid from 88 to 75; the operator logged "vibration slightly up, observe"; three days later it returned to 82 (self-recovered); another motor slid from 78 to 66 (upgraded to YJ1, inspection found bearing wear). The value of Watch is observing what should be observed and escalating what should be escalated — not every drift needs an immediate fix.
5. The 55-69 YJ1 Band: Inspect Within 24 Hours
What YJ1 means — alarm level one: the abnormal trend is confirmed and an inspection should confirm it; What YJ1 does — schedule an inspection within 24 hours: enter the plan, no middle-of-the-night trip; Why 24 hours — the risk is contained: not near-accident, but the confirmation cannot slip past a day; The YJ1 output — an inspection conclusion: hazard confirmed, or interference ruled out — written back to the alarm record; The boundary of YJ1 — inspection finds high risk and the score keeps falling to 54: upgrade to YJ2, handle in shift.
In one sentence: YJ1 is "inspect within 24 hours" — a confirmation window, not a leave-it window — the inspection conclusion must be written back.
A YJ1 example: One busbar temperature at 62 (YJ1): next-day infrared inspection confirmed a hot joint — planned into the repair schedule; if the inspection had shown the temperature still climbing fast, the score would have dropped to 50 the same day (YJ2, handle in shift). The 24 hours of YJ1 is time to confirm the hazard, not time to wait and see.
6. The 40-54 YJ2 Band: Handle in the Current Shift
What YJ2 means — alarm level two: the hazard is clear and needs handling in this shift; What YJ2 does — handle in the current shift: complete the intervention before shift handover; Why current shift — risk has escalated: a clear hazard handed to the next shift may miss the window; How YJ2 handles — load reduction, intensified monitoring, on-site verification: choose by hazard type; The boundary of YJ2 — no improvement after handling: the score slides to 39, upgrade to BJ1 shutdown repair.
In one sentence: YJ2 is handle in the current shift — a clear hazard must be acted on — the result and the score change must both be recorded.
A YJ2 example: One feeder overload at 48 (YJ2): the shift cut load by 20% and verified on site — the score recovered to 72 (handling effective); if the score had kept falling to 35 despite the cut (upgrade to BJ1, plan shutdown repair). The key to shift handling is feedback after the action — the score is an immediate test of effectiveness.
7. The 20-39 BJ1 Band: Shutdown Repair Within 48 Hours
What BJ1 means — alarm level one: high risk persists and the equipment needs a shutdown repair; What BJ1 does — shutdown repair within 48 hours: take the equipment out of service and fix it thoroughly; Why 48 hours — shutdown needs a production window: arranging the stop, spares and the repair plan takes time; What BJ1 repairs — by the diagnostic conclusion: replace, repair, calibrate — done in one pass; The boundary of BJ1 — risk worsening before repair: the score falls below 19, upgrade to BJ2 immediate shutdown.
In one sentence: BJ1 is a shutdown repair within 48 hours — the shutdown is not the goal; thorough treatment is — and the score stays watched through the repair.
A BJ1 example: One transformer winding temperature at 32 (BJ1): shutdown repair arranged within 48 hours — inspection found aging winding insulation; after replacement the score returned to 90. The 48 hours of BJ1 is time to organize the shutdown, not time to keep running — every extra hour of a high-risk device adds risk.
8. The 0-19 BJ2 Band: Shut Down Immediately
What BJ2 means — alarm level two: near-accident state; the equipment must stop now; What BJ2 does — shut down immediately: the equipment leaves service at once, personnel safety first; Why immediate — near-accident: every extra minute may cause an incident; How BJ2 executes — protection interlock plus manual confirmation: auto trip or manual emergency stop, per site procedure; What BJ2 follows — post-shutdown analysis: find the root cause, assess the damage, plan the repair.
In one sentence: BJ2 is immediate shutdown — near-accident leaves no room for "wait a bit" — safety first, root cause after the stop.
A BJ2 example: One cable joint at 12 (BJ2): shut down immediately — on-site inspection found severe overheating and carbonized insulation — one more run and it could catch fire. BJ2 is the lowest band and the only one that is not open for discussion — immediate shutdown is discipline, not advice.
9. Cross-Band Escalation: Crossing a Boundary Triggers Faster Action
What escalation is — a score sliding from a higher band to a lower one: the action escalates and the pace quickens; What triggers it — crossing a boundary: 84-69, 54-39, 19-0 — every step has a clear boundary; Why escalation matters — dynamic response: when the hazard worsens, handling no longer waits for the next shift; The escalation record — every step is logged: old score, new score, time and the triggered action; Escalation and de-escalation — a recovering score can step down: after effective handling the action relaxes.
In one sentence: cross-band escalation means a score crossing a boundary automatically speeds up the action — scores are dynamic, and so is the response pace.
An escalation example: One device's score slid all the way: 88 (Normal) → 72 (Watch) → 61 (YJ1) → 44 (YJ2) → 28 (BJ1) → 15 (BJ2) — every boundary crossing escalated the action once — the operator never waits for a supervisor order; the band dictates the execution. Cross-band escalation gives alarm handling an automatic rhythm — the score speaks, the action follows.
10. Reading the Standard-Code Reference and the Four-Dimension Impact Label
The standard-code reference — every alarm links to a standard basis: the corresponding GB or industry-standard clause — "what is this based on" is traceable; The four-dimension impact label — safety, equipment, production, environment: which dimensions are affected and how much; Safety impact — risk to people and equipment: whether electric shock or fire-level risk is involved; Equipment impact — equipment health damage: damage degree, repair cost and life impact; Production impact — shutdown and output risk: line impact, output impact, delivery impact; Environment impact — environmental compliance risk: emissions, noise and energy consumption against red lines.
In one sentence: the code reference answers "what is the basis", the four-dimension label answers "what is affected" — the score decides "how urgent", the label decides "what to care about".
A label example: One alarm: 48 (YJ2) plus a DL/T 596 clause reference plus a four-dimension label (safety: medium; equipment: high; production: low; environment: none) — the operator sees at once: equipment impact high, production impact low — handle the equipment issue in shift without stopping production. Labels turn an alarm from "one score" into "a decision card" — urgency, impact and action explained in one view.
11. Common Pitfalls: Four Traps in Using the Bands
Trap 1 — reading the score, not the trend — a single 63: a 63 that slid down from 88 and a 63 that climbed up from 55 are completely different; Trap 2 — Watch never reviewed — logged and forgotten: observation records no one reviews let drift become hazards; Trap 3 — no escalation across bands — still handling as YJ2 below 39: the pace fails to follow and a hazard slips into an accident; Trap 4 — labels ignored — only the score, not the impact: an alarm about equipment damage is logged as ordinary.
In one sentence: the four traps are reading the point not the trend, Watch never reviewed, no cross-band escalation and labels ignored — the first three misjudge urgency, the last misjudges the impact.
A trap example: In one project review, an alarm slid from 85 to 41 and the operator only saw "41, YJ2, handle in shift" — but by trend this was accelerating deterioration of 44 points — after handling, no one kept watching, and it fell to 28 (BJ1) the next day. Bands are a static scale; the trend is a dynamic signal — watch both, and the action is accurate.
12. Back to YESLON: How the Qianzhi V4.1 Bands Land
Qianzhi Engine V4.1 — ships with six-band mapping: five boundaries at 85/70/55/40/20, score to action mapped automatically; Taiyi coordination — automatic graded dispatch: YJ1 enters the inspection plan, YJ2 dispatches in shift, BJ1 schedules the shutdown, BJ2 interlocks an emergency stop; Handling closed loop — score changes recorded: a recovered score after handling proves effectiveness, and the result is written back to the alarm record; Label system — four-dimension impact and code reference travel with the alarm: the operator sees basis, impact and action at once; Difference from the SAR red line — the red line is an immutable national-standard bottom line: the bands are model-based composite scores, changing dynamically with data.
In one sentence: Qianzhi V4.1 is six-band mapping, automatic graded dispatch, a handling loop and four-dimension labels — alarms become "executable decision cards", not just a ring.
A landing example: One park adopted Qianzhi V4.1; after automatic graded dispatch, operators executed SLAs by band, misjudgment dropped and on-time handling improved. Bands do not burden operators — they replace "guessing how urgent it feels" with "executing by the scale" — the clearer the scale, the calmer the field.
Scope and Limitations
- The conclusions in this article are intended for LV distribution and electrical-safety sites. Standard numbers (DL/T 596) refer to their currently effective editions, and product parameters follow the latest FEXLINK selection handbook and product knowledge base.
- Quantitative criteria (protection zone, discharge and residual voltage, earth resistance, thresholds and grading) hold under the preconditions stated in this article. Where the site voltage level, earthing arrangement, environmental category or load profile differs, the figures must be recalculated. Specific configurations involving Qianzhi engine V4.1 should be verified against actual circuit parameters.
- Specific product models and parameters are subject to the latest selection handbook and product knowledge base; this article does not constitute selection or procurement advice.
- Standard numbers cited here refer to the currently effective editions; when a standard is revised, the related quantitative conclusions must be re-checked.
- Deployment and implementation for specific projects must be carried out by qualified engineers based on site survey and design drawings.
Frequently Asked Questions
Reading Qianzhi's Six Alarm Bands
A 63-point alarm pops up on the big screen — does the operator act now or just log it